The project
Pierina is a Barrick gold mine in the Peruvian Andes. Its heap leach pad had to be expanded to receive new ore.
Tie the new liner into the existing HDPE-lined pad, and work on almost vertical slopes.
2 mm LLDPE geomembrane, bentonite to prepare the subgrade where clay could not be placed, and a tie-in weld between phase 4 and the new phase 5.
Phase 5 commissioned in about 300 days and integrated into the existing system.
Gallery






More projects

Argentina · Mining · 2008–2021
Barrick · Veladero Mine, San Juan, Argentina
≈ 1.35 million m² in the 2017 and 2020 stages, at more than 4,000 m above sea level.
View project
Argentina · Mining · 2020
Lithium projects · Salar del Hombre Muerto, Argentina
≈ 600,000 m² of LLDPE geomembrane on two work fronts.
View project
Argentina · Canals and irrigation · 2015
Vialagro · Cinco Saltos, Río Negro, Argentina
≈ 75,000 m² of HDPE geomembrane along a stretch of about 2 km.
View projectMining