Lined Cinco Saltos canal in service

Río Negro, Argentina · Public works

Lining of the Cinco Saltos canal

≈ 75,000 m²

of HDPE geomembrane

≈ 2 km

of canal upgraded

90 days

construction period

Project data

Client
Vialagro (main contractor)
Location
Cinco Saltos, Río Negro, Argentina
Carried out by
SIGSA S.A. (headquarters, Argentina)
Year
2015
Area (approx.)
75,000 m²
Duration
90 days
Material
HDPE geomembrane on the bed, concrete on the slopes
Scope
Reshaping of the section and lining of a stretch of about 2,000 m
Products and services
Lining · Installation and quality control

The project

Less water lost for the city and for irrigation

01

Context

The canal carries water for consumption and irrigation in the Alto Valle, from Cinco Saltos toward Contralmirante Cordero.

02

Challenge

Seepage losses reduced the available flow and affected the urban area next to the canal.

03

Solution

Cleaning and reshaping of the section, concrete lining on the slopes and HDPE geomembrane with soil cover on the bed.

04

Result

The urban stretch is now lined, with lower seepage losses and better conveyance toward the irrigation area.

Gallery

The project in pictures

Cleaning and reshaping of the canal section
01 · Reshaping of the section, 2015
Geomembrane rolls at the edge of the canal
02 · Geomembrane rolls on site
Lining of the canal bed with geomembrane
03 · Lining of the bed
Lining progress along the canal
04 · Lining progress
Geomembrane anchor trench
05 · Anchor trench

More projects

Related projects

View all projects
Floating cover over an anaerobic sewage lagoon in Cipolletti
01

Argentina · Sanitation · 2010

Floating cover for odor control at a sewage plant

DPA Río Negro · Cipolletti, Río Negro, Argentina

≈ 30,000 m² of floating cover over an anaerobic lagoon.

View project
Veladero heap leach pad expansion during installation
02

Argentina · Mining · 2008–2021

High-altitude heap leach pad expansions

Barrick · Veladero Mine, San Juan, Argentina

≈ 1.35 million m² in the 2017 and 2020 stages, at more than 4,000 m above sea level.

View project
Oxidation ditch lined with geomembrane in Magdalena
03

Argentina · Industry · 2018

Rehabilitation of a concrete oxidation ditch

Nestlé · Magdalena, Buenos Aires, Argentina

HDPE geomembrane lining of a cracked ditch, in 45 days.

View project

Public works

Do you have a canal, irrigation or dam project?

Request a quote